Measure P
Measure P was approved on June 7th, 2016 to help modernize and improve the District's middle school and six elementary schools. Completed projects:- Blanchard window replacement project (completed 2017)
- Isbell science classrooms project (occupied December 2018)
- Barbara Webster parking lot project (opened August 2019)
- Isbell literacy center project (occupied August 2019)
- Grace Thille lunch shelter project (completed 2019)
- Classroom air conditioning at Barbara Webster, Blanchard, Glen City, Grace Thille, and Bedell
- Bedell electrical upgrades project (completed 2020)
- Glen City sidewalk replacement project (completed December 2020)
- Barbara Webster painting project (completed March 2021)
- Blanchard painting project (completed October 2021)
- Barbara Webster window replacement project at "science wing" (completed January 2022)
- Barbara Webster lunch shelter project (completed January 2022)
- Glen City playground equipment + surfacing (opening on May 12, 2022)
- Grace Thille hardscape replacement project (completed summer 2022)
- McKevett hardscape replacement project (completed summer 2022)
- Grace Thille playground surfacing project (completed summer 2022)
- Grace Thille painting project (completed fall 2022)
- McKevett painting project (completed winter 2023)
The following projects are currently underway or in the design phase:
- Isbell interim housing project (plans are DSA approved)
- McKevett electrical upgrade (punch list phase)
Bond Oversight Advisory Committee
We are actively seeking new members, as we currently only have two committee members! Please e-mail dhenning@santapaulausd.org to obtain an application for committee membership.The next meeting is scheduled for 5:00PM on August 22, 2023; the meeting will be conducted virtually.Xochitl Gomez, member-at-largeMatthew Inouye, member-at-large