McKevett Elementary School
Electrical Upgrade Project
The electrical service at McKevett Elementary School was recently upgraded to a 1,200A service, and the site's two existing, smaller services were eliminated. The upgraded service provides the necessary capacity to add air conditioning to the site's permanent buildings.
This project was approved by the Board on January 23, 2021. Construction efforts began in October 2021, and much of the project was completed during the summer of 2022. Ultimately, SCE provided the site's new service in February 2023.
The project was substantially completed in April 2023, and the project is now in the punch list phase.