• McKevett Elementary School
    Electrical Upgrade Project
     
    The electrical service at McKevett Elementary School will be upgraded to a 1,200A service, and the site's two existing, smaller services will be eliminated.  The upgraded service will provide the necessary capacity to add air conditioning to the site's permanent buildings in the future.
     
    This project was approved by the Board on January 23, 2021, and a construction contract was awarded on August 12, 2021.  Construction efforts began in October 2021 and have been in progress intermittently working around the school's schedule.  Much of the project was completed during the summer of 2022, and we are now awaiting new electrical service from SCE.  Expect this project to be completed during the autumn of 2022.
     
    New 3" Raceway In Cafeteria Attic
    3in Raceway In MPR Attic
     
    Single Line Diagram
    SLD